11th May 2018
Significant progress on the construction of our 37.6 MW wind farm in Vietnam
The construction works have been in full progress since the start of construction at the end of December 2017. Construction and project manager on site as well as in Großschirma, together with the specialists of ENERCON, are ensuring a smooth operation.
The access roads have been built to 70 %. 3 foundations of the planned 16 plants of the type ENERCON E-103 EP2 have already been concreted and 3 more, as well as the substation, are currently under construction.
4th January 2018
After a total development time of 6 years and numerous negotiations, the construction of the wind farm project Mui Dinh in the province Ninh Thuan started in December 2017.
eab New Energy GmbH developed and project planned the project to the current status together with its Vietnamese subsidiary wpv Wind Power Vietnam LLC.
The wind farm project Mui Dinh includes the construction of 16 plants of the type E103 from the manufacturer ENERCON with a hub height of 85m on an area of more than 7.6 ha as well as an own substation. The wind farm will therefore feed-in annually about 100,000 MWh of electrical energy into the high-voltage grid of EVN (Vietnam Electricity) and – in terms of figures – supply more than 25,000 households with renewable energy.
The wind farm “Mui Dinh” with its 37.6 MW makes a great contribution to the region and, as a commercially operated project, takes a pioneering role in the People’s Republic Vietnam.